| Duration (project Management) |
Article Index for Duration |
Information AboutDuration (project Management) |
|
Do not confuse duration with Work . E.g. it takes three days for a Snail-mail letter to arrive from point A to point B, whereas the work put into mailing it may be 0.5 hours. Strictly speaking, the phrase ''Duration of terminal element X is 5 days'' is incomplete. It fails to specify the following:
So the improved statement could read: I, Marek Kowalczyk, as of 27 March 2005 strongly believe that if I fully applied myself to competing terminal element X and worked 8 hours a day every day, including holidays, and had all the materials at hand, then I would have completed it in 5 calendar days. It may seem unwieldy to use such complicated statements, but lack of detail often leads to misunderstanding. SEE ALSO |
|
|