| Earned Value Management |
Article Index for Earned |
Website Links For Earned |
Information AboutEarned Value Management |
| CATEGORIES ABOUT EARNED VALUE MANAGEMENT | |
| project management | |
| management | |
| production and manufacturing | |
| SHOPPER'S DELIGHT | |
|
Earned value compares the work finished so far with the estimates made in the beginning of the project. This gives a measure of how far the project is from completion. By extrapolating from the amount of work already put into the project, the Project Manager can get an estimate on how much resources the project will have used at completion. This technique is related to the Critical Path concept. An alternative project performance measurement and management technique is Critical Chain , which utilizes Buffer Management instead. The reason is that the earned value management method does not distinguish between the progress on the project Constraint (i.e. its critical chain) from progress on the non-constraints (i.e. other paths in the Project Network ). This can sometimes lead the project manager to expedite non-critical work at the expense of critical work in pursuit of better earned value measures, resulting in delayed project completion. This is a case of Local Optimization , resulting from a lack of Subordination of Local Measure s to Global Measure s. To apply earned value to a project, the project manager needs the following primary data:
Generally, the Planned Values are based on labour costs only, and the Earned Values and Actual Costs are calculated on the same basis. When a task is complete, the Earned Value in respect of a task is set (allocated) to be equal to the Planned Value of the task, irrespective of the Actual Costs spent on its accomplishment. For tasks partly complete, it may be possible to measure the amount of work completed. In such cases, the Earned Value can be calculated accordingly as a fraction of the total Planned Value. Other alternative conventions exist for partially completed tasks, based on, for example:
Whatever the basis of calculation, the Earned Value for a project is the sum of the Earned Values for its separate tasks. From these data, the project manager can calculate: ; Cost Variance ( CV ) : , greater than 0 is good ; Schedule Variance ( SV ) : , greater than 0 is good If the cost or schedule variance deviates from the budget by more than a percentage threshold, then the project manager must provide an analysis of the cause, including corrective actions. Such an explanation is required even if the deviation is a favorable one, to ensure that any tradeoffs made are visible. For example, more staff could be hired to complete a task faster but the cost may be higher. The threshold percentage is set by each individual project but is typically 10 percent. ; Cost Performance Index ( CPI ) : : < 1 means that the cost of completing the work is higher than planned (bad) : = 1 means that the cost of completing the work is right on plan (good) : > 1 means that the cost of completing the work is less than planned (good or sometimes bad). Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, since the CPI is being measured against a poor baseline. Management or the customer may be upset with the planners since an overly conservative baseline does not free up available funds for other purposes, and the baseline is also used for manpower planning. ; Schedule Performance Index (SPI) : , greater than 1 is good : or : ; Estimate At Completion (EAC) : EAC is the manager's projection of total cost of the project at completion. : ; To-Complete Performance Index (TCPI) : The TCPI projects what the CPI will be for the remaineder of the project based on the manager's projection of subsequent performance. The TCPI should be compared to the CPI. Any significant difference should be accounted for to explain why the manager projects either improved or degraded performance in the future. : ; Independent Estimate At Completion (IEAC) :The IEAC is a metric to project total cost using the performance to date to project overall performance. This can be compared to the EAC, which is the manager's projection. : : or : LIMITATIONS Earned value cannot easily be applied in all circumstances. Here are some project management situations where EV is not straightforward:
SEE ALSO EXTERNAL LINKS |